FIP-41 QA Milestone Checklist
The milestone checklist tracks the QA tasks that need to be completed prior to moving the Epic or story into a new status
Task | Deliverables | Notes |
---|---|---|
Links |
|
|
Github repo |
|
|
Project wiki |
|
|
QA Epic |
|
|
QA Test Plan |
|
|
Scoping | Create QA stories and subtasks Estimate stories | Each story should be unit of work that is deliverable in a 2 week sprint. An initial estimate should be included with every story. |
Meeting - Test plan review | Meeting held with Dev Team and Product Manager to review test plan |
|
Test Development |
|
|
fio.test branch | Branch for new tests created on fio.test |
|
System Testing | fio.test enhanced with functional tests Tests run cleanly Functional tests well documented (in fio.test) and reviewed with team |
|
Performance testing | Work with Dev Lead to create performance test plan fio.test enhanced with performance tests |
|
History node testing | Test against node with V1 History and confirm no errors in log file (add results to Dev Spec) |
|
Meeting - Testing code and results review |
| |
UAT |
|
|
Merge to develop and install on DEV |
| |
QA complete |
| |
Devnet |
|
|
Devnet testing |
| |
Testnet |
|
|
Smoketest |
| |
Testnet QA validation |
| |
Mainnet |
|
|
Mainnet QA validation |
|