[FIP-43] Project Management Milestone Checklist

[FIP-43] Project Management Milestone Checklist

The milestone checklist tracks the development tasks that need to be completed for new features.

 

 

Task

Deliverables / Notes

 

 

Task

Deliverables / Notes

Kickoff

 

 

 

Project wiki

 

Project wiki created

[FIP-43] Update get_fee validation

Epic

 

Epic created for project

https://fioprotocol.atlassian.net/browse/BD-3502

Requirements and Scoping

 

 

 

Meeting - Kickoff meeting

 

Kickoff meeting held with Product Manager to review requirements

https://fioprotocol.atlassian.net/browse/BD-3751

Review FIP

 

FIP reviewed and moved to Accepted status

https://fioprotocol.atlassian.net/browse/BD-3752

Master Release Schedule

 

Update master release schedule with feature actions and endpoints

https://fioprotocol.atlassian.net/browse/BD-3753

SDKs

 

 

 

SDKs

Excluded
Included
Epic created to track SDK Release (if changes are needed for new features)
Stories created for any needed SDK updates (new getters or actions. These should have been documented by devs during feature development)

N/A no changes needed

UAT

 

 

 

Feature complete

 

All bugs and outstanding items completed
Work with QA to confirm JS tests run cleanly against DEV server

https://fioprotocol.atlassian.net/browse/BD-4187

Product Management

 

Signoff from Product Management

https://fioprotocol.atlassian.net/browse/BD-3755

 