The milestone checklist tracks the QA tasks that need to be completed for new features
Task | | Checklist | Status / Deliverables |
---|
Links | | | |
QA Epic or Story | QA Test Plan | | Scoping | Project manager will create initial QA epic or story | Jira Legacy |
---|
server | System JIRA |
---|
serverId | 5f0d8161-d4cf-3d17-96b1-53b2b2b5013d |
---|
key | BD-3731 |
---|
|
|
QA Test Plan | | | |
Scoping | | - Create QA stories and subtasks for items in Feature QA Milestone Checklist
- Estimate stories
| |
Meeting - Test plan review | | - Meeting held with Dev Team and Product Manager to review test plan
| |
Feature Testing | | | |
fio.test branch | | - Branch for new tests created on fio.test
| |
Feature Testing | | - fio.test enhanced with functional tests
- Tests run cleanly
- Functional tests well documented (in fio.test) and reviewed with team
| |
Performance testing | | - Work with Dev Lead to create performance test plan
- fio.test enhanced with performance tests
| |
History node testing | | - Test against node with V1 History and confirm no errors in log file (add results to Dev Spec)
| Jira Legacy |
---|
server | System JIRA |
---|
serverId | 5f0d8161-d4cf-3d17-96b1-53b2b2b5013d |
---|
key | BD-4227 |
---|
|
|
Meeting - Testing code and results review | | - System and performance tests and results reviewed with Dev team
| |
UAT | | | |
Merge to develop and install on DEV | | - Rebase feature branch and merge to develop for UAT testing
- Install release on DEV server
| |
QA complete | | - All bugs and outstanding items completed
- JS tests completed and run cleanly against DEV server
| |
...