[FIP-27] NFT Signatures Project Plan

Item

Description

Epic/Story

Estimate

Start

End

Item

Description

Epic/Story

Estimate

Start

End

Initiative

 

https://fioprotocol.atlassian.net/browse/BD-2569

 

6/14

8/17

Development

 

 

 

 

 

Technical Design

  • Initial design

5

6/16

6/23

Development

 

 

20

6/22

7/20

 

 

 

 

 

 

QA

 

 

 

 

 

Initial dev tests

  • Initial tests coded by developer

 

5

7/20

7/27

Paweł PM tests

  • Development of initial QA Happy and Sad path tests

 

5

7/27

8/3

Additional QA Tests

  • Additional tests from Functional Spec and QA

 

3

8/3

8/6

Performance testing

  • Performance tests for new tables and getters

 

4

8/3

 

Security

 

 

 

 

 

Handoff to Halborn

  • Code freeze for contract code and handoff to Halborn

 

 

8/3

 

Security Audit

  • Halborn security audit of fio.staking contract

 

10

8/3

8/17