FIO Token/Domain

Task

Status

ETA

Owner

Define requirements

Pawel Mastalerz

Define FIP

Pawel Mastalerz

Technical approach

Eric Butz

Development and testing (FIO Contract)

Eric Butz

Deploy to FIO Testnet

  • July 14-21 - RM and msig approval - Done

  • Targeting contract execution 7/27 - Done

  • regoracle msig 8/16

    • Delayed. Waiting on BPs to create msig.

Eric Butz

Testnet UAT

New date. Waiting on BPs to execute. Also, need more stable oracle to test.

  • Aug 17 - Aug 26

Pawel Mastalerz

Identify initial oracles

Pawel Mastalerz

Identify initial custodians

Pawel Mastalerz

Deploy to Ethereum/Polygon Testnet

Eric Butz

Deploy Testnet Oracles code

  • June 1 - Initial deploy to BPs - Done

  • July 15 - Aug 12 - QA and fixes from Aleph1

  • Aug 15 - Deploy to oracles

  • Aug 15-26 - BP oracle testing

    • Update: I think this will take 2+ weeks.

Eric Butz

System QA and testing

  • Still finding a number of bugs with the contracts and oracle.

  • Aug 3-19 deploy and test updated erc20 and erc721 contracts

Deploy to FIO Mainnet

(Tentative)

  • Aug 9 - Aug 17 - msig 1 (actions)

    • Rob and Borden were out. Waiting on Rob to create msigs. Updated dates

    • (new date0

  • Aug 17 - Aug 24 - msig 2 (permissions)

    • (new date)

  • Mainnet launch - Sep 9 - msig 3 (contracts) (depends on final QA from all other wrapping applications)

    • (new date)

Eric Butz

Deploy to Ethereum/Polygon Mainnet

  • Deploy - Aug 13

  • QA and Testing - Aug 14-22

Eric Butz

Deploy Mainnet Oracles code

  • Aug 4-15 - BPs setup mainnet accounts

  • Mainnet launch + 5 days - Test and debug mainnet wrapping with oracles

Eric Butz

TOKEN: Add initial liquidity to Uniswap, add WFIO to token lists

Pawel Mastalerz

TOKEN: List WFIO on CMC/Coingecko/others

Pawel Mastalerz

DOMAIN: Enable support on OpenSea

Pawel Mastalerz

Launch Dashboard support

Mainnet + week

George Worrell

Oracle Wrapping status admin tool

  • July 11-15 - Transition to Aleph1

  • Aug 22 - Sep 9 - CI deployment, QA and Debugging

  • Sep 2 - Testnet release (changed date)

    • Aleph One has limited resources to work on this in August.

  • Sep 9 - Mainnet launch + 5 days - Test and debug mainnet Wrapping status tool

Eric Butz

Launch marketing

Ash Howe