FIO Token/Domain

Task

Status

ETA

Owner

Define requirements

Status
colourGreen
titleComplete

Pawel Mastalerz

Define FIP

Status
colourGreen
titleComplete

Pawel Mastalerz

Technical approach

Status
colourGreen
titleComplete

Eric Butz

Development and testing (FIO Contract)

Status
colourGreen
titleComplete

May 1 - Jul 15

Eric Butz

Deploy to FIO Testnet

Status
colourYellow
titleIn progress

  • July 14-21 - RM and msig approval

  • Targeting contract execution 7/27

,
  • regoracle msig 8/3

.

Eric Butz

Testnet UAT

Status
colourYellow
titleIn progress

Pushed out one week. Need to execute a regoracle msig on Testnet prior to UAT.

  • Aug 3 - Aug 12

Pawel Mastalerz

Identify initial oracles

Status
colourGreen
titleComplete

Pawel Mastalerz

Identify initial custodians

Status
colourGreen
titleComplete

Pawel Mastalerz

Deploy to Ethereum/Polygon Testnet

Status
colourGreen
titleComplete

Eric Butz

Deploy Testnet Oracles code

Status
colourYellow
titleIn Progress

  • June 1 - Initial deploy to BPs - Done

  • July 15 - Aug 12 - QA and fixes from Aleph1

  • Aug 15 - Deploy to oracles

  • Aug 15-19 - BP oracle testing

Eric Butz

Deploy to FIO Mainnet

Status
colourRed
titleNot started

(Tentative)

  • July 29 - Aug 4 - msig 1 (actions)

  • Aug 5 - Aug 11 - msig 2 (permissions)

  • Mainnet launch - Aug 24 - msig 3 (contracts) (depends on final QA from all other wrapping applications)

Eric Butz

Deploy to Ethereum/Polygon Mainnet

Status
colourRed
titleNot started

  • Deploy - Aug 13

  • QA and Testing - Aug 14-22

Eric Butz

Deploy Mainnet Oracles code

Status
colourRed
titleNot started

  • Aug 4-15 - BPs setup mainnet accounts

  • Mainnet launch + 5 days - Test and debug mainnet wrapping with oracles

Eric Butz

TOKEN: Add initial liquidity to Uniswap, add WFIO to token lists

Status
colourRed
titleNot started

Pawel Mastalerz

TOKEN: List WFIO on CMC/Coingecko/others

Status
colourRed
titleNot started

Pawel Mastalerz

DOMAIN: Enable support on OpenSea

Status
colourRed
titleNot started

Pawel Mastalerz

Launch Dashboard support

Status
colourYellow
titleIn progress

July 1stMainnet + week

George Worrell

Oracle Wrapping status admin tool

Status
colourYellow
titleIn progress

  • July 11-15 - Transition to Aleph1

  • Jul 14 - Aug 12 - CI deployment, QA and Debugging

  • Aug 12 - Testnet release (changed date)

  • Aug 22 - Mainnet release - Test deploy

  • Mainnet launch + 5 days - Test and debug mainnet Wrapping status tool

Eric Butz

Launch marketing

Status
colourRedYellow
titleNot startedIn progress

Ash Howe